Project features

Start:

End:

Dec 2021

Dec 2023

Location:

Client:

Uzbekistan

Abu Dhabi Future Energy Company PJSC – Masdar

The GoU has been implementing a large-scale RE strategy to deploy in the next 10 years up to 5 GW of cost effective and environment-friendly solar generation to meet the increasing demand for electricity in Uzbekistan. As part of this initiative, GoU mandated ADB and IFC to help prepare and auction three different sites, which was won by Masdar on a design, build, finance, operate basis. Masdar contracted Juru to undertake solar measurement campaign for 12 months at the Bukhara PV project sites. 

Services provided

Assignment 1. Solar Measurement Campaign

  • Conduct solar measurement campaign and data collection for 12 months by installing  automatic weather stations including a 3m height- tower with wind sensors and a PV module
  • Deliver monthly reports in accordance with IEC 61724-1:2017 standard that covers bankable measurement data with 99.5% accuracy and data analysis of global & reflected horizontal irradiance, ambient temperature and relative humidity

Assignment 2. Geotechnical Investigations

  • Carry out geotechnical investigations with a total 15 boreholes (5 meters depth) and 38 ERT, TRT tests
  • Submit Geotechnical Report with recommendations for designing PV area

Assignment 3. Topographical Survey

  • Perform a detailed topographical survey within 673 Ha area including access roads and transmission lines using Unmanned Aerial drones adhering to specified grid mesh requirements